Water

City
Luoyang
Country
China
Year
2015
Associated ranges
Features
Large Diamater Pipes
Geographical zones
Asia
Markets
Water
Project specifications
Public contracting authority: Luoyang Beikong Raw Water Co. Ltd.
Construction company: The 3rd Engineering Company of China Tiesiju Civil Engineering Group (CTCE) Co. Ltd.
Length: 22.6 KM
Application: raw water transferring
DN: 1 600
This project is to transfer the raw water from the Gu county Reservoir downstream to the water plant in Luoyang high-tech zone and Guanlin water plant, totally 132 km.
Project features
- Over long-distance water transferring
- Large diameter and big scale
Outcome
- Provide 22.6 km of K8 DN1600 DI pipes
- STD joints were used, which resulted in quick installation
- No delay for the project
Service
- Provide optimized logistic plan
- Carry out soil corrosion test
- Technical assistance on site